Historically we have installed CO alarms in our properties as part of other planned workstreams, however haven’t instigated a specific programs until this time. Our stock is approximately 90percent gas heated so we have taken the imitative to install CO alarms during the Gas servicing to achieve compliance.

Currently our gas servicing program program has a very high access rate owing to a more robust access procedure underpinned by legislative requirement. While we are making headway on electrical servicing access we still fall behind that of the gas.

By taking advantage of the better gas access rate, we are hopeful we will ensure compliance to the new CO requirement however it will take the remainder of the annual service cycle to achieve and be documented.

We feel the electrical access problems would make 100% compliance by the deadline impossible,